2026 District Infrastructure Replacement Project Areas and Schedule

The 2026 DIRP projects are organized into four construction schedules: DIRP 2026 #1, DIRP 2026 #2, DIRP 2026 #3, and DIRP 2026 #4.

DIRP 2026 #2 was bid on February 4, 2026, and includes an optional scope expansion—via change order—to incorporate DIRP 2026 #4.
The bid tabulation for DIRP #2 is available here:

2026 DIRP #2 Bid Tabulation

DIRP 2026 #1 was opened at 10:00 AM on February 27, 2026, at the District office.

DIRP #1 also includes a scope expansion, via change order, to incorporate DIRP 2026 #3

2026 Construction Schedule

DIRP 2026 #1 Schedule

  • Bid Opening: 02/27/2026
  • Letter of Recommendation to Board: 03/04/2026
  • Notice of Award Signed: 03/12/2026
  • Notice to Proceed / Preconstruction Meeting: 03/26/2026
  • Project Completion (DIRP #1): 08/24/2026

DIRP 2026 #2 Schedule

  • Mobilization: March 31 – April 4, 2026
  • Asphalt Milling: April 6
  • Waterline Installation: April 6 – April 10, 2026
  • Project Completion (DIRP #2): 08/05/2026

DIRP 2026 #3 – Draft Schedule

  • District, Lakewood, Denver Water Reviews: 04/06/2026 – 06/29/2026
  • Change Order into DIRP #1: 08/24/2026
  • Project Completion (DIRP #3): 11/20/2026

DIRP 2026 #4 – Draft Schedule

  • District, Lakewood, Denver Water Reviews: 04/06/2026 – 06/29/2026
  • Change Order into DIRP #2: 08/05/2026
  • Project Completion (DIRP #4): 11/03/2026

2026 Construction Map:

The image is a map showing water main lines for the Green Mountain Water and Sanitation District, planned for 2026.