2026 District Infrastructure Replacement Project Areas and Schedule
The 2026 DIRP projects are organized into four construction schedules: DIRP 2026 #1, DIRP 2026 #2, DIRP 2026 #3, and DIRP 2026 #4.
2026 Construction Schedule
DIRP 2026 #1 Schedule
- Mobilization: TBD
- Asphalt Milling: TBD
- Waterline Installation: TBD
- Project Completion (DIRP #1): August 2026
DIRP 2026 #2 Schedule
- Waterline Installation, S Braun St: Waterline Intallation Completed, Paving starting 6/5
- Waterline Installation, S Arbutus St: Waterline Intallation Completed, Paving to be scheduled.
- Waterline Installation, W Tennesse Dr: Started June 4
- Waterline Installation, S Yank St: Starting Late June/July
- Waterline Installation, S Zang, W Florida Pl, & S Zang Ct: Starting Late June/July
- Waterline Installation, S Yank St: Starting Late June/July
- Project Completion (DIRP #2): 08/05/2026
DIRP 2026 #3 – Draft Schedule
- District, Lakewood, Denver Water Reviews: 04/06/2026 – 06/29/2026
- Change Order into DIRP #1: 08/24/2026
- Project Completion (DIRP #3): 11/20/2026
DIRP 2026 #4 – Draft Schedule
- District, Lakewood, Denver Water Reviews: 04/06/2026 – 06/29/2026
- Change Order into DIRP #2: 08/05/2026
- Project Completion (DIRP #4): 11/03/2026
2026 Construction Map: